Build an electrical load schedule
List running and startup loads, voltage, phase, dedicated circuits, plug types, and simultaneous use.
- Shore-power rating
- Generator continuous and surge capacity
- Panel and circuit schedule
- HVAC and refrigeration startup loads
- Lighting, pumps, water heater, POS, and small appliances
Document propane demand
Use qualified professionals and manufacturer data.
- Appliance BTU input
- Cylinder or tank capacity
- Regulators, piping, valves, and shutoffs
- Cage, separation, ventilation, and travel position
- Leak checks and authority review
Size water for the service day
Fresh-water capacity is only half the plan; wastewater, refill, heating, pumping, and cleaning matter too.
- Expected handwashing and warewashing use
- Food prep and beverage use
- Fresh and wastewater tank capacity
- Pump, accumulator, heater, fill, vent, and drain
- Approved fill and disposal locations